More noise expected at new ferry terminal

Night work extended through Feb. 15

 

January 22, 2020

Photo courtesy of WSDOT

The new Mukilteo ferry terminal is expanding in-water night work through Feb. 15, when the fish migration window closes.

Loud noises and night construction will continue at the new Mukilteo ferry terminal as crews continue work on the wing walls. The City of Mukilteo approved another noise variance for this work.

Manson Construction said the crew fell behind schedule during the holiday season. The additional noise request is due to a continued need for overnight welding activities to occur during extreme low tides. These low tides occur between the hours of 6 p.m. to 4 a.m.

To take advantage of these tides, the construction company will extend nighttime work for 18 more days, from Jan. 27 to Feb. 15, when the...



For access to this article please sign in or subscribe.



 